The following PMP® exam sample question is taken from the Free PMP Exam Simulator at http://free.pm-exam-simulator.com/ - The answer is at the very bottom:
------------------------------
What is risk tolerance?
A.) Risks created by tolerating customer behavior.
B.) Willingness to accept varying degrees of risk.
C.) Risks created by zero tolerance.
D.) Being tolerant if stakeholders are willing to accept risks.
------------------------------
Hint: Look for the “least strange” answer.
------------------------------
All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com/ and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at http://www.free-pm-exam-questions.com./ We are a PMI Registered Education Provider.
Until next time,
Cornelius Fichtner, PMP
President, OSP International LLC
The Project Management PrepCast™ - http://www.project-management-prepcast.com/
The Project Management Podcast™ - http://www.project-management-podcast.com/
ANSWER AND EXPLANATION:
The correct answer is B
Explanation: Do you feel that A, C and D are odd? Correct, they are and they were included intentionally. Sometimes you can expect to find some “funny” answer choices.
Risk tolerance is the stakeholders' willingness to accept varying degrees of risk. Choice B is the only correct answer to this question.
Reference: PMBOK4 - pg:276
Agile Questions? Project Management Questions? CMMI too! Get the answers here! Brain gems from a SCRUM Master (CSM), SCRUM Professional (CSP) and PMP. Proof that I am certifiable.
Wednesday, November 2, 2011
Friday, August 19, 2011
Critical Path Mapping: A Basis for Agile Project Management
As certified project management professionals, we are intimately familiar with the processes necessary to define the critical path of a project. How does that apply when managing an Agile project? One of the best approaches I have seen is a two phased approach to critical path definition. Phase 1 – Define the High Level Critical Path for the overall project. Phase 2 – Define the critical paths within each sprint as you initiate each sprint. This approach allows you to define the steps necessary to complete the overall project as well as have more control over each sprint by defining the critical path within each sprint. Whether you define a single overall PERT chart for the project, or separate PERT charts for each sprint is your choice. Let’s take a look at a simplistic example:Project Goal: To build an information management system that will allow the user to communicate with other users, schedule events, manage registration for events and post comments related to the events.
Overall Project Tasks:
Task ID | Task Name |
1 | Construct Test Environment (Architecture) |
2 | Construct Production Environment (Architecture) |
3 | Construct Test Environment (Software) |
3a | Construct Registration Module |
3b | Construct Scheduling Module |
3c | Construct Communications Module |
3d | Test Registration Module |
3e | Test Scheduling Module |
3f | Test Communications Module |
4 | Migrate to Production |
5 | Announce Launch |
Project PERT Network Chart:
This network diagram demonstrates the project as 13 weeks in length. Tasks 2, 3 and 5 create the critical path.
Sprint 1 – PERT Network Chart:
This network diagram demonstrates this sprint as 4 weeks in length. Tasks 3b and 3e are the critical path.
Sprint 2 – PERT Network Chart:
This network diagram demonstrates this sprint as 4 weeks in length. Tasks 3a and 4 are the critical path.
This simple example helps demonstrate how the scrum master can define the critical path of the overall project as well as for each sprint. By defining each sprints critical path, the scrum master can ensure that the appropriate resources are working each task. Focusing on those critical path tasks allows the scrum master to prioritize impediment management, scope changes, issues and risks impacting critical path tasks on a sprint by sprint basis.
Saturday, June 18, 2011
Free PMP Exam Sample Question
The following PMP® exam sample question is taken from http://www.free-pm-exam-questions.com - The answer is at the very bottom:
PMBOK Section: Estimate Costs
Process Group: Planning Process Group
Question Type: Calculation
Knowledge Area: Cost Management
Difficulty Level: Easy
Question: You are managing an amusement park development project. You have received the following estimates for site excavation and area development activity that is critical to the success of your project. The most likely estimate is $100,000, the optimistic estimate is $90,000, and the pessimistic estimate is $120,000. What is the expected activity cost?
A. $101666
B. $100000
C. $120000
D. $90000
Reference: PMBOK4 - pg:173
Subscribe to:
Comments (Atom)


