The following PMP® exam sample question is taken from the Free PMP Exam Simulator at http://free.pm-exam-simulator.com/ - The answer is at the very bottom:
------------------------------
What is risk tolerance?
A.) Risks created by tolerating customer behavior.
B.) Willingness to accept varying degrees of risk.
C.) Risks created by zero tolerance.
D.) Being tolerant if stakeholders are willing to accept risks.
------------------------------
Hint: Look for the “least strange” answer.
------------------------------
All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com/ and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at http://www.free-pm-exam-questions.com./ We are a PMI Registered Education Provider.
Until next time,
Cornelius Fichtner, PMP
President, OSP International LLC
The Project Management PrepCast™ - http://www.project-management-prepcast.com/
The Project Management Podcast™ - http://www.project-management-podcast.com/
ANSWER AND EXPLANATION:
The correct answer is B
Explanation: Do you feel that A, C and D are odd? Correct, they are and they were included intentionally. Sometimes you can expect to find some “funny” answer choices.
Risk tolerance is the stakeholders' willingness to accept varying degrees of risk. Choice B is the only correct answer to this question.
Reference: PMBOK4 - pg:276
Agile Questions? Project Management Questions? CMMI too! Get the answers here! Brain gems from a SCRUM Master (CSM), SCRUM Professional (CSP) and PMP. Proof that I am certifiable.
Subscribe to:
Post Comments (Atom)
from where i can get free questions of integration management
ReplyDeleteplz help asap