The following PMP® exam sample question is taken from http://www.free-pm-exam-questions.com - The answer is at the very bottom:  
PMBOK Section: Estimate Costs                                 
Process Group:     Planning Process Group                                         
Question Type:     Calculation                                    
Knowledge Area: Cost Management                                     
Difficulty Level:   Easy                                                                                                          
Question: You are managing an amusement park development project. You have received the following estimates for site excavation and area development activity that is critical to the success of your project. The most likely estimate is $100,000, the optimistic estimate is $90,000, and the pessimistic estimate is $120,000. What is the expected activity cost?                                                                                                                       
            A. $101666                                                                                                          
            B. $100000                                                                                                          
            C. $120000                                                                                                          
            D. $90000                                                                                                            
Reference: PMBOK4 - pg:173